This Page contains all the timetables published for the project, with the
most recent at the top. To access a timetable, click on one of the links below.
Logan Health Study
Timetable July, 2002
Logan Health Study Timetable
03/15/02
Logan Health Study Timetable
12/23/01 - Firm dates for major milestones
Milestone Chart 10/30/01 - DPH
Milestones
Timetable 2001-2002 - Being developed
Timetable 6/28/00 - Original Timetable
Logan
Health Study Timetable July, 2002
This timetable is based on prior timetables, and was updated with
information provided at the CAC Meetings. The Work Completed before the
"Indefinite Delay" imposed by the Massachusetts budget funding cut in
July, 2002 are shown. The dates for incomplete work are marked
"Delayed".
Basically, all work was completed to the point that the interview process was
about to begin when the funding was cut.
Changed information is in maroon.
To view prior target dates, use one
of the links above. Links are available from the table to get detailed
information.
Task |
Target Date |
Responsible |
Comments |
Status |
Hire Project
Coordinator |
January, 2001 |
MDPH |
Greg Merriman was assigned January, 2001 |
Completed |
Review available
environmental data at Massport |
October, 2001
|
MDPH |
Done by Mass DPH |
Completed |
Finalize details
of Community Advisory Committee |
October, 2001
|
MDPH |
First CAC Meeting was held 10/30/01 |
Completed |
PBHG Under
contract with MDPH |
December, 2001
|
MDPH |
|
Completed 12/17/01 |
Finalize Survey
Instrument Design |
Early March, 2002
|
MDPH/PBHG |
This will be done by PHRG |
95% Complete;
Delayed |
Task |
Target Date |
Responsible |
Comments |
Status |
Conduct Pilot Test
of Survey Instrument Administration and Accuracy |
Early March, 2002
|
PBHG |
Has Occured in random population around
Portland, ME, Jetport |
Completed |
Determine best
methods of categorizing exposure opportunities |
Early March, 2002 |
MDPH |
Decide on impact of distance, flight patterns,
available data, etc. |
Original Target
May 1, 2002;
Delayed |
Finalize sample
size and sampling plan |
Draft of Plan by early February, 2002 |
MDPH |
Sample size is estimated currently at 2700 |
Completed |
Create Written
Status Report #1 |
Early February, 2002 |
MDPH |
This will be input to CAC meeting |
Completed as of February, 2002 |
Task |
Target Date |
Responsible |
Comments |
Status |
Interim
discussions with CAC, PBHG, MDPH |
By early March, 2002 |
MDPH |
Discussions will be about draft sampling plan
and interview methods |
In Process;
Delayed
|
CAC Meeting
(Second) |
March 13, 2002 |
MDPH |
|
Complete |
Telephone
Interviews by Public Health Resource Group (PHRG) begin |
Original Target Date was
Early June, 2002 |
PBHG |
These will be the first interviews for the Logan Health Study. |
Delayed |
CAC Meeting (Third) |
May 14, 2002
(Tentative) |
MDPH |
|
Delayed |
Logan
Health Study Timetable 03/15/02
This timetable is based on prior timetables, and is updated with
information provided at the CAC Meeting of March 13, 2002. Changed target dates
are in maroon. To view prior target dates, use one
of the links above. Links are available from the table to get detailed
information.
Task |
Target Date |
Responsible |
Comments |
Status |
Hire Project
Coordinator |
January, 2001 |
MDPH |
Greg Merriman was assigned January, 2001 |
Completed |
Review available
environmental data at Massport |
October, 2001
|
MDPH |
Done by Mass DPH |
Completed |
Finalize details
of Community Advisory Committee |
October, 2001
|
MDPH |
First CAC Meeting was held 10/30/01 |
Completed |
PBHG Under
contract with MDPH |
December, 2001
|
MDPH |
|
Completed 12/17/01 |
Finalize Survey
Instrument Design |
Early March, 2002
|
MDPH/PBHG |
This will be done by PHRG |
By May 1, 2002 |
Task |
Target Date |
Responsible |
Comments |
Status |
Conduct Pilot Test
of Survey Instrument Administration and Accuracy |
Early March, 2002
|
PBHG |
Will occur in random population around
Portland, ME, Jetport |
By May 1, 2002 |
Determine best
methods of categorizing exposure opportunities |
Early March, 2002 |
MDPH |
Decide on impact of distance, flight patterns,
available data, etc. |
By May 1, 2002 |
Finalize sample
size and sampling plan |
Draft of Plan by early February, 2002 |
MDPH |
Sample size is estimated currently at 2700 |
By May 1, 2002 |
Create Written
Status Report |
Early February, 2002 |
MDPH |
This will be input to CAC meeting |
Completed as of February, 2002 |
Task |
Target Date |
Responsible |
Comments |
Status |
Interim
discussions with CAC, PBHG, MDPH |
By early March, 2002 |
MDPH |
Discussions will be about draft sampling plan
and interview methods |
In Process |
CAC Meeting
(Second) |
March 13, 2002 |
MDPH |
|
Complete |
Telephone
Interviews by Public Health Resource Group (PHRG) begin |
Early June, 2002 |
PBHG |
These will be the first interviews for the Logan Health Study. |
Early June, 2002 |
CAC Meeting (Third) |
May 14, 2002
(Tentative) |
MDPH |
|
Future |
Logan
Health Study Timetable 12/23/01
This timetable is based on the contents of a BEHA communication . To view
the communication, click
here.
Task |
Target Date |
Responsible |
Comments |
Status |
Hire Project
Coordinator |
January, 2001 |
MDPH |
Greg Merriman was assigned January, 2001 |
Completed |
Review available
environmental data at Massport |
October, 2001
|
MDPH |
Done by Mass DPH |
Completed |
Finalize details
of Community Advisory Committee |
October, 2001
|
MDPH |
First CAC Meeting was held 10/30/01 |
Completed |
PBHG Under
contract with MDPH |
December, 2001
|
MDPH |
|
Completed 12/17/01 |
Finalize Survey
Instrument Design |
Early March, 2002
|
MDPH/PBHG |
This will be done by PHRG |
Winter, 2001 |
Task |
Target Date |
Responsible |
Comments |
Status |
Conduct Pilot Test
of Survey Instrument Administration and Accuracy |
Early March, 2002
|
PBHG |
Will occur in random population around
Portland, ME, Jetport |
To Do |
Determine best
methods of categorizing exposure opportunities |
Early March, 2002 |
MDPH |
Decide on impact of distance, flight patterns,
available data, etc. |
To Do |
Finalize sample
size and sampling plan |
Draft of Plan by early February, 2002 |
MDPH |
Sample size is estimated currently at 2700 |
To Do |
Create Written
Status Report |
Early February, 2002 |
MDPH |
This will be input to CAC meeting |
To Do |
Task |
Target Date |
Responsible |
Comments |
Status |
Interim
discussions with CAC, PBHG, MDPH |
By early March, 2002 |
MDPH |
Discussions will be about draft sampling plan
and interview methods |
To Do |
CAC Meeting
(Second) |
March 12, 2002 |
MDPH |
|
To Do |
Telephone
Interviews by Public Health Resource Group (PHRG) begin |
Early June, 2002 |
PBHG |
These will be the first interviews for the Logan Health Study. |
Early June, 2002 |
Return to Top of Page.
Milestone Chart
10/30/01
Task |
Status |
Proposed Timeline |
Hire Project
Coordinator |
Greg Merriman was assigned January, 2001 |
Completed |
Review available
environmental data at Massport |
Done by Mass DPH |
Completed |
Finalize details
of Community Advisory Committee |
First CAC Meeting was held 10/30/01 |
Completed |
Finalize Survey
Instrument |
This will be done by PHRG |
Winter, 2001 |
Telephone
Interviews by Public Health Resource Group (PHRG) begin |
This will be done by PHRG |
Spring, 2002 |
Return to Top of Page.
Timetable 2001-2002.
This timetable is being developed, and will be published as soon as available.
For developments October-November, 2001, go to the Community
Advisory Committee.
Return to Top of Page.
Timetable 6/28/00.
The information in this timetable was originally generated at the Winthrop Public
Meeting 6/28/00. As seen below, it will be updated as required. The tasks on this timetable will be picked
up in Timetable 2001-2002.
Task |
Depends On |
Target Date
As of 6/28/00 |
Revised Target
Date
As of Nov, 2000 |
Status |
Acquire and Evaluate MassPort Environmental Data |
|
July, 2000 |
To Be Determined |
11/10/00 Intern hired and active. |
Hire an Environmental Scientist to be the Project
Coordinator |
Hiring Process |
August, 2000 |
January, 2001 at the earliest |
02-07-00 - Environmental Scientist
Hired.
11/10/00 -
Budget and other problems delayed finding a qualified candidate.
|
Design Survey Instrument, methodologies, sample size,
timetable, etc. |
Environmental Scientist on board |
Sept, 2000 |
Early 2001 |
11/10/00
Needs Environmental Scientist |
Get independent Peer Review signoff |
Design, etc. |
Oct, 2000 |
To Be Determined |
11/10/00
Needs Environmental Scientist |
Begin Study interviews |
Signoff |
Nov. - Dec., 2000 |
To Be Determined |
11/10/00
Needs Environmental Scientist |
Community Advisory Group Meeting |
Environmental Scientist on board |
August-Sept, 2000 |
To Be Determined |
11/10/00
Needs Environmental Scientist |
Update to the Town of Winthrop |
Design Complete |
Sept, 2000 |
To Be Determined |
11/10/00
Needs Environmental Scientist |
|
|
|
|
|